Warning: unserialize() expects parameter 1 to be string, array given in /var/www/html/nioh/wp-content/plugins/convertplug/modules/modules-functions.php on line 615

Warning: unserialize() expects parameter 1 to be string, array given in /var/www/html/nioh/wp-content/plugins/convertplug/modules/modules-functions.php on line 615

Warning: unserialize() expects parameter 1 to be string, array given in /var/www/html/nioh/wp-content/plugins/convertplug/modules/modules-functions.php on line 615

Warning: unserialize() expects parameter 1 to be string, array given in /var/www/html/nioh/wp-content/plugins/convertplug/modules/modules-functions.php on line 615

Warning: unserialize() expects parameter 1 to be string, array given in /var/www/html/nioh/wp-content/plugins/convertplug/modules/modules-functions.php on line 615

It is stated in the Asbestos Regulations:

Under 15(1):

Cleaning is done under controlled conditions ensuring that

  1. Dry-brushing, scraping, sanding and abrasion techniques are not used;
  2. Where reasonably practicable, high-pressure water jetting is not used unless in conjunction with a suitably profiled hood that limits dispersal of contaminated water and, if the said jetting is used, that suitable control methods are used in accordance with regualtion 13(2)(b); and
  3. When fungicidal solution or moss killer is applied, a standing time of 24 hours or any other period specified by the manufacturer is allowed, and a low-pressure hose is used after such a period to keep the sheets wet whilst employing a stiff broom any similar means to remove any moss or lichens.

Under 13(2):

With regard to the contamination of water with asbestos

  1. That any water that is contaminated with asbestos as a result of work being performed is passed through a filtration system before being released into any environment or water system; and
  2. That a suitable water filtration system is used which will ensure that the asbestos being released or entering into any environment or water system is reduced as far as is reasonably practicable;
  3. That contaminated parts of the filtration system, when discarded, are disposed of as asbestos waste; and
  4. That appropriate measures are taken to prevent the release of asbestos dust into the environment arising from the transport of asbestos.